CITY OF SALEM
North Street Improvement Project Update - November 27, 2006
We anticipate that major construction will begin again in March or April of 2007. This meets with the schedule provided by Mass Highway's contractor. The project is still on schedule to be completed in 2008.
North Street (Rt. 114) Construction Project Information
General
The Project is being constructed with federal and state funding under the direction of the Massachusetts Highway Department (MHD). The Contractor is A. R. Belli, Inc. of Newtonville, Massachusetts. The design engineer is Earth Tech who will be providing support to the City and MHD during construction.
Contract Status
Construction Commencement: August 2006
Final Completion Date: July 2008
Contacts
Massachusetts Highway Department (MHD) Representatives:
Area Manager: Ted Gibson
Resident Engineer: Michael Cannata
City Engineer:
A.R. Belli, Inc. Superintendent:
Bill Duryea
Communications
· All onsite communications are to go through the MHD representative, Michael Cannata or the City’s Engineering Office.
· For Emergency calls during non-working hours the Salem Police Department will have emergency numbers for MHD, the City Engineer, and the Contractor.
Mass Highway Notifications
· Written notification:
Patricia A. Leavenworth, P.E.
519 Appleton Street
Arlington, MA 02476
Tel. No. 781-641-8300
Field Office Location
To Be Determined
Schedule Restrictions
October Work Restrictions
Winter Shutdown
_________________________________________________________________________
|