Temporary Closure for Part of Canal Street Moving Early to Phase 2

Phase 1 now expected to end around June 28; Phase 2 (Hersey Street to Forest Avenue) begins same week
phase2

The temporary closure of part of Canal Street for the roadway reconstruction project is ahead of schedule as work progresses quickly. MassDOT and the project contractors now anticipate ending the closure of Phase 1 (Ocean Avenue to Hersey Street) on or around June 28, about three weeks ahead of schedule.

From approximately June 28 through August 4 no through traffic will be possible on Canal Street from Hersey Street to Forest Avenue. During that time, detours will be posted allowing through traffic to travel through the corridor via Broadway and Ocean Avenue. Additional police officers will be located on the detour route to monitor speeds and traffic flow. Please drive with caution at all times.

All Canal Street businesses remain open for business during this time period, with the exception of McDonalds, which is temporarily closed to carry out a large renovation project. Please help support our Canal Street businesses during this important roadway improvement project.

While the rest of the Canal Street Roadway Improvement Project can be accomplished while allowing through traffic to continue, the state of deterioration under the roadway in this one 600-foot stretch is substantial. To reconstruct the roadway in a manner that will provide the most long-lasting improvement, the contractor will be excavating to 30-inches below the road surface, more than twice the standard excavation depth. The roadway will be filled with a light concrete fill, instead of conventional fill, and a stabilizing high-strength geo-tech fabric will then be installed over the top of the fill from curb to curb. A final paving layer will then go over the geo-tech fabric.

The deterioration of this portion of the roadway has occurred as peat and loose soils under the pavement have consolidated and sunk over time, while underground utilities such as storm drains and conduits have kept the road surface elevated in places. The resulting roadway surface is highly uneven and not safe. The more substantial improvement possible through this temporary closure of this portion of the street will help eliminate this problem on a more long-term basis than conventional engineering methods.

For additional updates and to sign up for the weekly project email update, please visit http://www.buildingsalem.com/canal-street-roadway-improvement-project/.